Palestinian Energy and Natural Resources Authority

Palestinian Energy and Natural Resources Authority (PENRA)  |  Funded by The World Bank

Smart Meters Monitoring Dashboard

ESPIP - Advanced Metering Infrastructure roll-out at the distribution companies

Installed smart meters against planned quantities, by distribution company and batch

Developed by: Amer Braik

The World Bank
←  All projects Smart Meters installation - ESPIP Reporting date  31 Aug 2026
 
Planned meters
 
 
Installed
 
 
Remaining
 
 
Installed in the last period
 
 
 
 
 
 
 

Plan and progress

How many meters are planned, how many are installed so far, and how many are left. Every figure here follows the filters, so narrowing to one company or one meter type narrows these too.

Installed and remaining by distribution company

Progress by distribution company

Installation over time

Running total of installed meters at every reporting date. The chart follows the filters above, so you can watch a single company or a single meter type build up. Hover anywhere on the chart for the figures on that date.

Cumulative installed meters

Batch and meter type

Progress by batch and meter type

Detailed breakdown

Breakdown by

Definitions

Programme

ESPIP
Smart meters delivered under the Electricity Sector Performance Improvement Project. Quantities are split into an original Batch-1 and an addendum Batch-2, and progress is reported weekly.

Batch and meter type

Batch-1
ESPIP original planned quantity.
Batch-2
ESPIP addendum quantity, contracted after Batch-1.

Distribution companies

HEPCO
Hebron Electric Power Company
JDECO
Jerusalem District Electricity Company
NEDCO
Northern Electricity Distribution Company
SELCO
Southern Electricity Company
TDECO
Tubas Electricity Distribution Company

Measures and delivery stage

Planned
Quantity the distribution company is contracted to install, original quantity plus any addendum.
Installed
Meters installed and reported at the reporting date. Figures are running totals, not additions.
Remaining
Planned quantity less the meters installed so far.
Fully installed
The whole planned quantity for that group has been installed.
Installation under way
Installation has started but the planned quantity is not yet complete.
Not started
No meters installed against the planned quantity so far.